Working in the area of Porter Square to Beacon St. Start to build Cross Walks on North (odd #'s) side of Somerville Ave & across the side streets that are also on that side of the Avenue.
Week of 3/15/10
Building Cross Walks on the North side streets and North side of Somerville Ave in the Porter Sq to Beacon St area.
Build Cross Walks on the North side of Wilson Sq.
Work on the completion of building the Wilson Sq island.
Misc Traffic signal work @ Dane St & School St, and misc. conduits Bow St to Bow St.
Week of 3/22/10
Build Cross walks on the North (odd #'s) side of the Avenue and North side streets, from Wilson Square to Lowell St.
Start to Build Cross Walks on the South (even #'s) side of the Avenue and South side streets, Porter Sq to Beacon St.