Location: Hall St. from Cherry St. to Cedar St.
Construction Schedule: Summer 2020 - December 2020, with final paving in Spring 2021 (subject to change)
Work Hours: Approximately 7 a.m. - 5 p.m.
Scope of Work:
- Replace existing 6” water main with new 8” ductile iron water main
- Replace existing VC (Vitrified Clay) 10” sewer with new 10” diameter PVC sewer
- Evaluate drainage needs and extend existing storm drain if needed
- Reconstruct the roadway, including cement concrete sidewalks and curb ramps. Consider raised crosswalks and bump-outs for ADA compliance and improved road safety.