Cold weather update: Learn about preventing frozen water pipes here. For tips on staying safe during extreme cold, visit our cold weather page here.
Cold weather update: Learn about preventing frozen water pipes here. For tips on staying safe during extreme cold, visit our cold weather page here.
City contractors are working to upgrade the water main beneath Broadway between Temple St. and Boston Ave.
The water main in this area dates as far back as the late 19th/early 20th century. Old pipes suffer from tuberculation, a form of corrosion, which reduces the amount of water that the pipe can supply.
Through this project, water mains in the neighborhood will be upgraded through a combination of replacement and rehabilitation (including processes such as cured-in-place pipe lining). Some water services (lines connecting individual properties to the water main) will also be replace through this project.
Recent Updates
Thursday (10/23) and Friday (10/24) Utility Trench Paving on Broadway Terrace
This Thursday and Friday, City contractors plan to mill and repave utility trenches on Broadway Terrace.
Schedule of Work (subject to change due to weather or other factors)
What To Expect During Paving
On-site crews and police details are available to help and may be able to assist you in getting to/from your home while work is underway.
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400 with questions.
Week of October 14th Overnight Utility Trench Paving (Updated 10/16 w/ revised schedule)
This upcoming week, beginning Tuesday, October 14th, City contractors plan to repave utility trenches (portions of the roadway where excavation for water utility work took place previously) on Broadway between Main Street and Cedar Street and on Medford Street between Broadway and Norwood Avenue.
Schedule of Work
Paving will take place overnight between the hours of 7 p.m. and 5 a.m. A preliminary day-by-day scheduling including specific locations of work is included below.
This schedule is subject to change due to weather or other factors.
What To Expect During Paving
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 ext. 5400 with questions.
Thank you for your patience and understanding while we complete this essential work to improve our City’s infrastructure.
September 2025 Update
As of this month crews have completed all water utility upgrades planned as part of this project. Crews are now working throughout the neighborhood to restore segments of roadway and sidewalk that were affected by earlier utility work.
Crews are expected to complete this work and vacate the neighborhood over the before the end of October.
May 2025 Update
Since April crews have been making progress on water main updates along Medford Street between Broadway and Trull Street. This work is expected to be completed in late June.
Meanwhile, crews has start preparing for work on Broadway. Crews will start at Temple Street and work west toward Cedar Street. This work is expected to continue through the summer and into the fall.
March 2025 Update
As early as the week of March 31st or soon after, City contractors will begin preliminary work on the remaining water main upgrades planned as part of this project.
What to Expect
Crews will begin work by setting up temporary water mains along:
Properties along the above stretch will be connected to water utilities via temporary bypass (somervillema.gov/bypass) to ensure they continue to receive service throughout the work.
Some brief interruption of water service may be required during construction (notification will be provided approximately 48 hours in advance.)
Temporary parking restrictions will be required to facilitate work. Please observe posted signage.
Locations of Work (2025 Spring/Summer Season)
Questions?
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 x 5400.
January 2025 Update
Since the Spring of 2024, City contractors have been working along the Broadway corridor to restore and upgrade water utilities.
Crews are rehabilitating these systems through a combination of cleaning/lining existing water mains as well as by replacing select segments of old main and installing new pipes.
What has been completed so far?
Cleaning and Lining Work
Installation of New Utilities
What work remains? (Spring '25)
Crews are expected to resume work in April (weather permitting) to complete the remaining utility work.
Cleaning and Lining Work
Work will resume in the spring and run through the 2025 construction season (approximately April through October).
Daily work hours are approximately 7 a.m. to 3 p.m.
Broadway is expected to remain open to through traffic for the duration of the project.
During certain phases of the project, there may be associated parking restrictions. Notification of any parking restrictions will be posted no less than 48 hours in advance.
Temporary Water Bypass - Some residences may require temporary water bypass to be installed to ensure continued delivery of water service while new mains are installed.
Water Service Interruptions - Brief interruptions to water service will be required during the project.
Sign-up for City Alerts - Receive important notifications about this project and work in your area.
Visit our new construction page - Get a comprehensive look at work across the city.
Sign-up for the City's Construction Newsletter - Receive a monthly digest on infrastructure work across Somerville.
Follow us on Twitter - Tweets about curb-cuts, culverts, and more.
Please submit website feedback using this form. Be sure to include:
Thank you for your feedback!