Active Work
Scheduled and Locations of Work
Check back soon for planned 2025 work.
Construction Impacts:
- CIPP Lining Only - Affected residences are asked to limit their water usage during work hours on the date when work is taking place on the stretch where their home located
- affected residents will receive a secondary flyer with more information this request approximately 24 hour prior to work on their street
- On-street parking will be restricted during construction.
- Please observe posted signage.
- Periodic road closures may be required.
- Access will be maintained for pedestrians/residents
- Trash/recycling pick-ups and deliveries will not be affected.
If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 x 5400
How It Works
Each year the City inspects a portion of our sewer and drainage system to identify areas in need of rehabilitation. While more critical issues are addressed via emergency repairs, regular rehab and maintenance typically takes place the following year through our Sewer Pipeline and Manhole Rehabilitation Program.
Pipelines and manholes are rehabilitated using a combination of methods, including but not limited to the following:
- Injection Grouting – acrylic grout is pressure injected through a defect in the pipe, forming an impermeable barrier
- Cured In Place Pipe (CIPP) Lining – a flexible liner is inserted inside the existing pipe, inflated, and then hardened, forming a smooth surface inside the existing pipe
- Open Trench Excavation – crews will dig down to and expose existing pipe, remove the defective section or full length of pipe, and then install new pipe
- Spot Repair – similar to Open Trench Excavation, crews will dig a small trench, remove a short section of pipe, and install a new section of pipe
- Manhole Lining & Sealing – epoxy or cementitious material is applied to the inside of the manhole as a coating, restoring structural integrity and waterproofing the manhole
When excavation is required for construction, City contractors will pave the impacted area with a temporary course of asphalt immediately following the work. They will then return roughly a year later and perform final surface restoration.
Affected Streets 2025
Work is scheduled to occur on portions of the following streets:
Street |
Status |
Street |
Status |
Franklin Street |
Upcoming |
Franklin Avenue |
Upcoming |
Myrtle Street |
Upcoming |
Florence Street |
Upcoming |
Lincoln Avenue |
Upcoming |
Mount Pleasant Street |
Upcoming |
Mount Vernon Street |
Upcoming |
Perkins Street |
Upcoming |
Schedule of Work
This work is expected to begin in late May and continue through the summer. Residents will receive additional notification prior to work beginning on their street. Daily work hours are approximately 7 a.m. to 4 p.m.
Anticipated Impacts
Streets and sidewalks are expected to remain open for the duration of the project. Lane closures, lane shifts, and parking restrictions may be implemented as needed. Driveway access will be maintained.
Excavation may generate moderate noise during work hours (typically between 7 a.m. and 4 p.m.) throughout the project area. Pipe lining may produce a bubblegum-like odor that will dissipate quickly once the process is complete.
Stay Informed
Residents in impacted areas will receive notification via flyers and community alerts prior to work starting in their area.
Sign up for the City alert system to receive notifications about disruptive construction, snow emergencies, and major events planned for your neighborhood: somervillema.gov/alerts
Have questions? Email construction@somervillema.gov, call the Engineering Division at (617) 625-6600 ext. 5400, or call 311.